11.05.2021 |  Construction Updates Carrington Hill, May 2021 Upon the recovery of the COVID lockdown, the construction team is pushing full steam ahead. Building C has completed all the external cladding and brickworks. The electrical, plumbing and... See More
30.04.2021 |  Construction Updates 1975, April 2021 The following is the progress of the works to date: - Framing: 100% Completed - Masonry works: 100% Completed - Roofing installation: 90% Completed - Services rough in: 80% Completed - External... See More
23.07.2020 |  Construction Updates Eastbridge, July 2020 The following is the progress of the works to date: The team at D5 have made fantastic progress with some of the project milestones to date summarised as below: Rendering to external walls is... See More
23.07.2020 |  Construction Updates Gardenia Park, July 2020 Concrete slab, 100% completed Termite protection, 100% completed In-ground services, 100% completed Framing is currently underway, 20% completed Services have commenced. Project... See More
18.06.2020 |  Construction Updates Eastbridge, June 2020 With the colder weather settling in, construction work has not stopped on site. The team at D5 have made fantastic progress with some of the project milestones to date summarised as below: -... See More
10.06.2020 |  Construction Updates Gardenia Park, June 2020 Underground electricals – 100% completed Concrete slab 70% completed Termite protection 50% completed Drainage/Plumbing – 40% completed Framing is anticipated to... See More
10.06.2020 |  Construction Updates Eastbridge, May 2020 The team at D5 has been continuing business as usual and have made fantastic progress with some of the project milestones to date summarised as below: External cladding installation is at 80%... See More
15.01.2020 |  Construction Updates Eastbridge, January 2020 We are pleased to provide the progress achieved on site to date for Eastbridge. The basement works are completed with the ground floor slab in place Framing is well underway with TH 6 to 10... See More