Carrington Hill, May 2021
We are pleased to provide the progress achieved on-site to date for Carrington Hill.
Upon the recovery of the COVID lockdown, the construction team is pushing full steam ahead.
Building C has completed all the external cladding and brickworks. The electrical, plumbing and mechanical roughing are completed and it is ready for fit off. Waterproofing and tiling are also 100% complete. Joinery and stairs are progressing as scheduled and we aim to complete the Building C block around June / July 2021.
Regarding Building A & B, it is following closely after Building C. Roof plumbing works have been installed and the construction team is currently installing the external cladding and windows.