Eastbridge, January 2020

  |  Construction Updates

We are pleased to provide the progress achieved on-site to date for Eastbridge.

We are pleased to provide the progress achieved on site to date for Eastbridge.

  • The basement works are completed with the ground floor slab in place
  • Framing is well underway with TH 6 to 10 completed.
  • Steel works is at 50% completion
  • External blockworks is at 50% completion

We are pleased to attached photos taken from the site this week, showing the progress to date.

We will continue to provide you with regular construction updates leading up to settlement.