The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
Gardenia Park, July 2020
We are pleased to provide the progress achieved on-site to date for Gardenia Park.
- Concrete slab, 100% completed
- Termite protection, 100% completed
- In-ground services, 100% completed
- Framing is currently underway, 20% completed
- Services have commenced.
Project completion is still anticipated to be achieved by April 2021.
We are pleased to attached photos taken from the site this week, showing the progress of the groundwork to date.
We shall keep you updated on progress in the coming months and look forward to sharing regular updates on your future home at each milestone reached.