Bored piers are complete. Capping beams have been successfully installed. Retaining walls are now finished. Inground plumbing works are well underway. Bulk…
Gardenia Park, June 2020
We are pleased to provide the progress achieved on-site to date for Gardenia Park.
-
Underground electricals – 100% completed
-
Concrete slab 70% completed
-
Termite protection 50% completed
-
Drainage/Plumbing – 40% completed
-
Framing is anticipated to commence in a few weeks time
Project completion is anticipated to be achieved by April 2021.
We are pleased to attached photos taken from the site this week, showing the progress of the groundworks to date.
We shall keep you updated on progress in the coming months and look forward to sharing regular updates on your future home at each milestone reached.