11.04.2022 |  Project Photos Alfreda Modern design and timeless craftsmanship come together in perfect harmony. This beautifully crafted Alfreda townhouse represents the ultimate progression of luxury living. Nestled in a highly... See More
12.01.2022 |  Project Photos Carrington Hill Carrington Hill redefines contemporary urban living in the sought-after suburb of Box Hill in Melbourne’s east. Inspired exterior design celebrates sleek lines and contemporary forms within... See More
12.01.2022 |  Project Photos 1975 Step into a 1975 residence, and there is an immediate sense of depth and dimension. High ceilings, abundant sunlight, and a range of textural finishes create a layered sense of beauty. These are... See More
29.09.2021 |  Project Photos Gardenia Park – Boronia The architecture of Gardenia Park is inspired by the surrounding green character of Boronia, from the terraces and windows offering views of the neighbouring parks, to the use of subtle colours... See More
28.04.2023 |  Construction Updates Cascade, April 2023 - Townhouses 8 & 9 are up to the Second-floor frames- Townhouses 10-14 frames have all been completed- Windows have been installed for all townhouses that have completed their frames- The... See More
16.01.2023 |  Construction Updates Settled! Highmont, Dec 2022 The Townhomes at Highmont are all settled during Dec 2022! We at BHC Property would like to extend our warmest congratulations to all the purchasers. We know how exciting it is to own a new... See More
09.08.2022 |  Construction Updates Highmont, July 2022 The following is the progress of the works to date for the Highmont project: - New services connection 90% completed - External render and cladding 90% completed - Tiles and flooring 75% coverage... See More
29.06.2022 |  Construction Updates The Avenue, June 2022 The following is the progress of the works to date: Internal plasterboard installation - 90% completed Internal staircase - 90% completed Waterproofing to wet areas – 20% completed Tiling to wet... See More
29.06.2022 |  Construction Updates Highmont, June 2022 The following is the progress of the works to date for the Highmont project: - Entry door and hardware installed - Balcony waterproofing 50% finished - Balcony balustrade installed 50% - Painting... See More
01.06.2022 |  Construction Updates The Avenue, May 2022 The following is the progress of the works to date: External cladding - 95% completed Internal plasterboard installation 60% completed Internal staircase - 20% completed Waterproofing to wet areas... See More
26.05.2022 |  Construction Updates Highmont, May 2022 The following is the progress of the works to date: - Insulation for all units finished - Understairs doorway installed - Plaster wall and ceiling completed 80%- External cladding and render... See More
03.05.2022 |  Construction Updates Cascade, April 2022 Due to the shortage of raw materials across the industry, there have been some production and delivery delays of the LGS steel frames. Our team has been working endlessly trying to secure new... See More