We are pleased to provide the progress achieved on-site to date for Cascade.

  • – Townhouses 8 & 9 are up to the Second-floor frames
    – Townhouses 10-14 frames have all been completed
    – Windows have been installed for all townhouses that have completed their frames
    – The roofing for townhouses 6, 7, 10-14 are all to be completed soon.

Please see below photos taken from the site: