– Townhouses 8 & 9 are up to the Second-floor frames– Townhouses 10-14 frames have all been completed– Windows have been installed…
The Avenue, June 2022
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
- Internal plasterboard installation – 90% completed
- Internal staircase – 90% completed
- Waterproofing to wet areas – 20% completed
- Tiling to wet areas 40% completed
- The driveway is anticipated to be poured by the end of the month. Landscape works to commence after.
Project completion is now forecasted to be achieved by August/ September 2022.