The Avenue, June 2022

  |  Construction Updates

We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.

The following is the progress of the works to date:

  • Internal plasterboard installation – 90% completed
  • Internal staircase – 90% completed
  • Waterproofing to wet areas – 20% completed
  • Tiling to wet areas 40% completed
  • The driveway is anticipated to be poured by the end of the month. Landscape works to commence after.

Project completion is now forecasted to be achieved by August/ September 2022.