The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
GlenHolm, Feb 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Wall frames for all townhouses have been completed, marking progress in our infrastructure.
- Framing inspection is the next step, ensuring quality and safety standards.
- Scaffold installation is scheduled for later this week, prioritising worker safety and site efficiency.
- Roof batten and sheet delivered, currently installing.
- Lock-up procedures to commence shortly, securing townhouses against external elements and preserving the integrity of our workmanship.