Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
GlenHolm, Feb 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Wall frames for all townhouses have been completed, marking progress in our infrastructure.
- Framing inspection is the next step, ensuring quality and safety standards.
- Scaffold installation is scheduled for later this week, prioritising worker safety and site efficiency.
- Roof batten and sheet delivered, currently installing.
- Lock-up procedures to commence shortly, securing townhouses against external elements and preserving the integrity of our workmanship.