All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
GlenHolm, Feb 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Wall frames for all townhouses have been completed, marking progress in our infrastructure.
- Framing inspection is the next step, ensuring quality and safety standards.
- Scaffold installation is scheduled for later this week, prioritising worker safety and site efficiency.
- Roof batten and sheet delivered, currently installing.
- Lock-up procedures to commence shortly, securing townhouses against external elements and preserving the integrity of our workmanship.
Please see below the photos taken from the site: