All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
GlenHolm, Jan 2024
We are pleased to provide the progress achieved on site to date for GlenHolm, Glen Iris.
We are pleased to bring you the first construction update for the GlenHolm development in 2024, showcasing the significant progress made on-site.
- First-floor wall frames for all townhouses have been completed
- Second-floor floor joists for TH08 – TH12 have been installed
- Second-floor floor joists for TH01 – TH07 will be delivered and installed over the next week
- Floorboards for the second floor of TH08 – TH12 will be delivered soon.