– Townhouses 8 & 9 are up to the Second-floor frames– Townhouses 10-14 frames have all been completed– Windows have been installed…
The Davis, Nov 2018
We are pleased to provide the progress achieved on site to date for The Davis.
– Ground floor stab is completed.
– Wall framing to the ground floor is completed. First-floor framing underway.
– Structural steel has commenced.
– Plaster/shaft liner has commenced.
– Insulation installation to basement ceiling has commenced.
– Civil drainage works have continued.
– Hydraulic and electrical cast in/rough us underway.
Construction completion is still on track to be August 2019.







