Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
The Davis, Nov 2018
We are pleased to provide the progress achieved on site to date for The Davis.
– Ground floor stab is completed.
– Wall framing to the ground floor is completed. First-floor framing underway.
– Structural steel has commenced.
– Plaster/shaft liner has commenced.
– Insulation installation to basement ceiling has commenced.
– Civil drainage works have continued.
– Hydraulic and electrical cast in/rough us underway.
Construction completion is still on track to be August 2019.







