All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
The Avenue, Mar 2022
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
– Roofing installation at 90% completion
– Brickwork installation to the ground floor is at 90% completed
– Electrical and hydraulic rough-in is currently at 90% completed
– Heating and cooling installation at 50% completed
– External cladding installation on top level 100% completed
– Solar panels for hot water units are installed on the top roof