Norfolk Park, Jan 2018 25.01.2018 |  Construction Updates We are pleased to provide you with the progress achieved on site.
30.08.2024 |  Construction Updates GlenHolm, Aug 2024 All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway…. See More
31.07.2024 |  Construction Updates GlenHolm, Jul 2024 Underground service installation in progress. Exterior rendering in progress, affected by heavy rainfall over the last few weeks. Staircase installation in… See More
30.06.2024 |  Construction Updates GlenHolm, Jun 2024 Rough-in Completion: All rough-in work has been completed, ensuring essential infrastructure is in place. Exterior Cladding: The installation of exterior cladding… See More