Roof plumbing installation in progress Roof insulation near completion. Glass sliding doors in production. Insulation and plasterboards are being installed on ground…
Norfolk Park, Dec 2017
We are pleased to provide you with the progress achieved on site.
Norfolk Park is taking fantastic shape with construction now in the final stage. External façade works are currently underway with floorboards being installed this week. Tiling works in each apartment are well underway with the aim to finish this week.
Plastering works are complete in all apartments with painting and electrical fit offs complete up to level 2. Appliances will be delivered and installed middle of January along with shower screens.