The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
Ashton Park, May 2018
We are pleased to provide you with the progress achieved on site so far.
The following tasks, operations, and processes were performed in the current period;
Below ground works:
o Site cut – COMPLETE
o Hydraulics & Civil works – IN PROGRESS
o Electrical works including NBN – IN PROGRESS
o Authority Connections works – IN PROGRESS
Ground Floor
o Surveyor Setout & Grids – COMPLETE
o Detail excavation for concrete pad footings – COMPLETE
o Structural Steel shop drawings and details – IN PROGRESS
Other
o Hoarding & Fencing – COMPLETE
o Concrete sleeper retaining walls – COMPLETE