Ashton Park, May 2018
We are pleased to provide you with the progress achieved on site so far.
The following tasks, operations, and processes were performed in the current period;
Below ground works:
o Site cut – COMPLETE
o Hydraulics & Civil works – IN PROGRESS
o Electrical works including NBN – IN PROGRESS
o Authority Connections works – IN PROGRESS
Ground Floor
o Surveyor Setout & Grids – COMPLETE
o Detail excavation for concrete pad footings – COMPLETE
o Structural Steel shop drawings and details – IN PROGRESS
Other
o Hoarding & Fencing – COMPLETE
o Concrete sleeper retaining walls – COMPLETE