Wall frames for all townhouses have been completed, marking progress in our infrastructure. Framing inspection is the next step, ensuring quality…
Ashton Park, May 2018
We are pleased to provide you with the progress achieved on site so far.
The following tasks, operations, and processes were performed in the current period;
Below ground works:
o Site cut – COMPLETE
o Hydraulics & Civil works – IN PROGRESS
o Electrical works including NBN – IN PROGRESS
o Authority Connections works – IN PROGRESS
Ground Floor
o Surveyor Setout & Grids – COMPLETE
o Detail excavation for concrete pad footings – COMPLETE
o Structural Steel shop drawings and details – IN PROGRESS
Other
o Hoarding & Fencing – COMPLETE
o Concrete sleeper retaining walls – COMPLETE