Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
Ashton Park, March 2018
Builders are on site now and have started site cut and preparing the site for footing construction and in ground plumbing works.
The following tasks, operations, and processes were performed in the current period;
Below ground works:
Site cut – COMPLETE
Hydraulics/Civil works – IN PROGRESS
Electrical works – COMMENCED
Ground Floor
Surveyor Setout & Grids – COMPLETE
Other
Hoarding & Fencing – COMPLETE
Concrete sleeper retaining walls – COMMENCED




