The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
Ashton Park, August 2018
We are pleased to provide you with the progress achieved on site so far.
The following tasks, operations and processes were performed in the current period;
Below ground works:
o Hydraulics & Civil works – COMPLETE
o Electrical works including NBN – COMPLETE & READY FOR CONNECTION
o Authority Connections works – IN PROGRESS
Ground Floor:
o Ground Floor Concrete Slab preparations (Building B) – COMPLETE
o Ground Floor Concrete Slab preparations (Building A) – IN PROGRESS
o Structural block walls (Building B) – COMPLETE
o Structural block walls (Building A) – COMPLETE
o Formwork to Level 1 (Building B) – COMPLETE
Other:
o Steel framing (Building B) – in production
o Steel framing (Building A) – Shop drawings in progress