Altus, April 2019
We are pleased to provide you with the progress achieved on site so far.
Level 3 slab has been poured. level 4 slab will be poured 29/04/2019. Services: Sewer connected.
We are currently anticipating settlement time in November / December 2019.
We will keep you posted as we progress through the next phase.