Wall frames for all townhouses have been completed, marking progress in our infrastructure. Framing inspection is the next step, ensuring quality…
Altus, April 2019
We are pleased to provide you with the progress achieved on site so far.
Level 3 slab has been poured. level 4 slab will be poured 29/04/2019. Services: Sewer connected.
We are currently anticipating settlement time in November / December 2019.
We will keep you posted as we progress through the next phase.