All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
Altus, April 2019
We are pleased to provide you with the progress achieved on site so far.
Level 3 slab has been poured. level 4 slab will be poured 29/04/2019. Services: Sewer connected.
We are currently anticipating settlement time in November / December 2019.
We will keep you posted as we progress through the next phase.