The Davis, September 2018
We are pleased to provide the progress achieved on site to date for The Davis.
- Blockwork to basement completed.
- Formwork for Ground floor slab underway.
- Services penetration set out for ground floor underway.
- Waterproofing to basement walls completed.
Construction completion is still on track to be August 2019.