The Davis, September 2018

14.09.2018   |  Construction Updates

We are pleased to provide the progress achieved on site to date for The Davis.

  • Blockwork to basement completed.
  • Formwork for Ground floor slab underway.
  • Services penetration set out for ground floor underway.
  • Waterproofing to basement walls completed.

Construction completion is still on track to be August 2019.

The Davis Construction The Davis Construction The Davis Construction The Davis Construction The Davis Construction

Related Articles

02.02.2026   |  Construction Updates

Mercer, January 2026

Roof plumbing installation in progress Roof insulation near completion. Glass sliding doors in production. Insulation and plasterboards are being installed on ground…

See More
02.02.2026   |  Construction Updates

Audrey, January 2026

Plastering and cladding completed. Tiling of wet areas near completion Stone benchtops are being installed. Joinery is being installed and near completion….

See More
02.02.2026   |  Construction Updates

Prime, January 2026

This is a kind reminder that your Purchaser Final Inspection is scheduled for Tuesday, 3 February 2026. Construction progress to date: Common driveway…

See More
BHC Property

Join our Newsletter

Enter your email to stay up to date with all our latest news

Contact Us

+61 3 9813 1863
enquiry@bhcproperty.com

179 Burwood Rd, Hawthorn VIC 3122

 
  • Home
  • About
  • Vision
  • Collections
  • Insights
  • Contact
Instagram Facebook

Site by Seesaw