The Davis, September 2018

14.09.2018   |  Construction Updates

We are pleased to provide the progress achieved on site to date for The Davis.

  • Blockwork to basement completed.
  • Formwork for Ground floor slab underway.
  • Services penetration set out for ground floor underway.
  • Waterproofing to basement walls completed.

Construction completion is still on track to be August 2019.

The Davis Construction The Davis Construction The Davis Construction The Davis Construction The Davis Construction

Related Articles

16.01.2023   |  Construction Updates

Settled! Highmont, Dec

The Townhomes at Highmont are all settled during Dec 2022! We at BHC Property would like to extend our warmest congratulations to…

See More
09.08.2022   |  Construction Updates

Highmont, July 2022

The following is the progress of the works to date for the Highmont project: – New services connection 90% completed – External…

See More
29.06.2022   |  Construction Updates

The Avenue, June

The following is the progress of the works to date: Internal plasterboard installation – 90% completed Internal staircase – 90% completed Waterproofing…

See More
BHC Property

Join our Newsletter

Enter your email to stay up to date with all our latest news

Contact Us

+61 3 9813 1863
enquiry@bhcproperty.com

179 Burwood Rd, Hawthorn VIC 3122

 
  • Home
  • About
  • Vision
  • Collections
  • Insights
  • Contact
Instagram Facebook

Site by Seesaw