All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
The Davis, June 2019
We are pleased to provide the progress achieved on site to date for The Davis.
Construction at The Davis is continuing to progress well with completion now anticipated for July. This is subject to favorable conditions or unforeseen delays.
Please understand that an exact settlement date cannot be provided until the Plan of Subdivision has been registered and the Certificate of Occupancy achieved.
We will continue to provide you with regular construction and timing updates leading up to settlement.
Current status of works on site are:
– Tiling to wet areas 100% completed
– Lifts installation 70% completed
– Stair installation 85% completed
– Painting to Internal walls 60% completed
– External landscaping works 50% completed
– Joinery installation to commence this weekend
– Floor coverings installation has been scheduled to commence in 2 weeks time
We have engaged settlement solution as our settlement agent. Should you have any question, regarding settlement matter, please do not hesitate to contact with the below details:
Contact: Monique / Ph: 03 8582 8972 / Email: monique@settlement-solutions.com.au