The Davis, August 2018

12.08.2018   |  Construction Updates

We are pleased to provide the progress achieved on site to date for The Davis.

The progress of works:

  • Bulk excavation is complete
  • Strip and pad footing are complete
  • Bored piers are complete
  • Capping beam and shotcrete are complete
  • Blockwork is 80% complete

Construction completion is still on track to be by August 2019.

The Davis The Davis The Davis The Davis The Davis

Related Articles

09.08.2022   |  Construction Updates

Highmont, July 2022

The following is the progress of the works to date for the Highmont project: – New services connection 90% completed – External…

See More
29.06.2022   |  Construction Updates

The Avenue, June

The following is the progress of the works to date: Internal plasterboard installation – 90% completed Internal staircase – 90% completed Waterproofing…

See More
29.06.2022   |  Construction Updates

Highmont, June 2022

The following is the progress of the works to date for the Highmont project: – Entry door and hardware installed – Balcony…

See More
BHC Property

Join our Newsletter

Enter your email to stay up to date with all our latest news

Contact Us

+61 3 9813 1863
enquiry@bhcproperty.com

179 Burwood Rd, Hawthorn VIC 3122

 
  • Home
  • About
  • Vision
  • Collections
  • Insights
  • Contact
Instagram Facebook

Site by Seesaw