– Townhouses 8 & 9 are up to the Second-floor frames– Townhouses 10-14 frames have all been completed– Windows have been installed…
The Davis, August 2018
We are pleased to provide the progress achieved on site to date for The Davis.
The progress of works:
- Bulk excavation is complete
- Strip and pad footing are complete
- Bored piers are complete
- Capping beam and shotcrete are complete
- Blockwork is 80% complete
Construction completion is still on track to be by August 2019.