Wall framing complete Roof trusses in progress Plumbing stack work underway Please see below the photos taken from the site:
The Davis, August 2018
We are pleased to provide the progress achieved on site to date for The Davis.
The progress of works:
- Bulk excavation is complete
- Strip and pad footing are complete
- Bored piers are complete
- Capping beam and shotcrete are complete
- Blockwork is 80% complete
Construction completion is still on track to be by August 2019.




