The following is the progress of the works to date: External cladding – 95% completed Internal plasterboard installation 60% completed Internal staircase…
The Davis, August 2018
We are pleased to provide the progress achieved on site to date for The Davis.
The progress of works:
- Bulk excavation is complete
- Strip and pad footing are complete
- Bored piers are complete
- Capping beam and shotcrete are complete
- Blockwork is 80% complete
Construction completion is still on track to be by August 2019.




