The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
The Avenue, May 2022
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
- External cladding – 95% completed
- Internal plasterboard installation 60% completed
- Internal staircase – 20% completed
- Waterproofing to wet areas – 20% completed
- Tiling to wet areas to commence soon
- Landscaping works will commence in early June
Project completion is now forecasted to be achieved by late July to early August 2022.
Settlement is anticipated to be around late August/early September 2022.