The Avenue, May 2022
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
- External cladding – 95% completed
- Internal plasterboard installation 60% completed
- Internal staircase – 20% completed
- Waterproofing to wet areas – 20% completed
- Tiling to wet areas to commence soon
- Landscaping works will commence in early June
Project completion is now forecasted to be achieved by late July to early August 2022.
Settlement is anticipated to be around late August/early September 2022.