– Townhouses 8 & 9 are up to the Second-floor frames– Townhouses 10-14 frames have all been completed– Windows have been installed…
The Avenue, May 2021
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
– In ground plumbing work is completed.
– Formwork for concrete slab is completed.
– Concrete slab pour is underway and will be completed in a week’s time.
– Structural steel framing is anticipated to commence next month.
Construction completion is currently anticipated to be by Quarter 2 of 2022.


