– Townhouses 8 & 9 are up to the Second-floor frames– Townhouses 10-14 frames have all been completed– Windows have been installed…
The Avenue, Feb 2022
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
– Roofing and windows installation at 90% complete
– Brickwork installation to the ground floor is at 80% completed
– Electrical and hydraulic rough-in is currently at 70% completed
– Heating and cooling installation underway · External cladding to commence soon
Project completion is forecasted to be achieved by July 2022.



