The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
The Avenue, April 2022
We are pleased to provide the progress achieved on site to date for The Avenue, Croydon.
The following is the progress of the works to date:
– Brickwork and roofing installation completed
– Electrical and hydraulic rough-ins completed
– Heating and cooling installation are 45% completed
– External cladding installation to the first floor 80% completed
– Insulation installation is 80% completed
– Plasterboard installation is to commence in early May
– Landscaping works are anticipated to commence from mid-May
Project completion is now forecasted to be achieved by late July 2022.