11.06.2025 |  Construction Updates Mercer, May 2025 Floor structure in first structure complete First floor wall framing in progress Windows ordered; preparing for installation Please see below the photos taken from the... See More
11.06.2025 |  Construction Updates Audrey, May 2025 Water meters installed Units 6-10 roof installation in progress Units 1-5 first floor framing in progress Please see below the photos taken from the... See More
11.06.2025 |  Construction Updates Prime, May 2025 External cladding complete Roof installation complete Gutters installed, downpipes in progress Wall insulation complete Internal plastering commenced Please see below the photos taken from the... See More
29.04.2025 |  Construction Updates Mercer, Apr 2025 Basement hydraulic and mechanical services in progress Basement stud framing in place Ground floor framing complete Floor structure of first floor in progress for rear units Please see below... See More
29.04.2025 |  Construction Updates Audrey, Apr 2025 Units 6-10 ground floor framing complete Units 6-10 first floor framing and party walls in progress Basement hydraulic and mechanical services in progress Basement ceiling insulation... See More
29.04.2025 |  Construction Updates Prime, Apr 2025 All window installation complete Staircase installation complete Second floor lightweight wall cladding complete Base coat render for ground floor Hebel walls complete Electrical rough-ins near... See More
31.03.2025 |  Construction Updates Mercer, Mar 2025 Basement ceiling insulation has been installed. Ground floor plumbing rough-ins are now in place. Ground floor steel and timber framing are nearing completion. Ground floor party walls have been... See More
31.03.2025 |  Construction Updates Audrey, Mar 2025 Steel structural members have been installed. Ground floor blockwork walls are currently in progress. Fire services equipment has been delivered. Timber frame materials have arrived... See More