Prime Construction Commencement

  |  Construction Updates

We are delighted to bring you the construction update for the Prime Prahran development, showcasing the progress made on-site.

  • Site cut and survey complete
  • Drainage works in progress, in-ground stormwater plumbing installed
  • Excavation for underground water tanks in progress
  • NBN conduits is complete
  • Preparation of concrete slab works in progress, and due to be poured before end of month
Please see below the photos taken from the site: