The following is the progress of the works to date: External cladding – 95% completed Internal plasterboard installation 60% completed Internal staircase…
Parkfield, Jan 2018
We are pleased to provide you with the progress achieved on site so far.
Unit 26-30 slabs have been poured. The Rest Pre-Slabs inspections have been approved. Unit 26-30 framing stage started.
80% of electrical mains have been completed and 80% of the drainage works have been completed.
We will keep you posted as we progress through the next phase.