All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
Parkfield, Apr 2019
We are pleased to provide you with the progress achieved on site so far.
Concrete reinforcement unit 1, 2, 8 and 9 have been completed and approved.
Steel (Brick wall above SF2) unit 20, 21, 24-30 have been completed and approved.
Please note that we won’t be able to accommodate any further changes at this stage. Currently anticipated settlement time will be October/November 2019.
We will keep you posted as we progress through the next phase.