The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
Mercer, Oct 2024
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Steel reinforcement for basement blockwork walls is in place
- Reinforcement for concrete columns is in place
- Concrete footings are complete
- Capping beams are complete
- Construction of concrete columns has commenced
- Basement turntable installation is in progress
Please see below the photos taken from the site:
![](https://bhcproperty.com/wp-content/uploads/2025/01/Image_20241018161850-1024x768.jpg)
![](https://bhcproperty.com/wp-content/uploads/2025/01/Image_20241018161855-1024x768.jpg)
![](https://bhcproperty.com/wp-content/uploads/2025/01/Image_20241018161906-1024x768.jpg)