Basement hydraulic and mechanical services in progress Basement stud framing in place Ground floor framing complete Floor structure of first floor in…
Mercer, Mar 2025
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Basement ceiling insulation has been installed.
- Ground floor plumbing rough-ins are now in place.
- Ground floor steel and timber framing are nearing completion.
- Ground floor party walls have been completed.