Floor structure in first structure complete First floor wall framing in progress Windows ordered; preparing for installation Please see below the photos…
Mercer, Mar 2025
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Basement ceiling insulation has been installed.
- Ground floor plumbing rough-ins are now in place.
- Ground floor steel and timber framing are nearing completion.
- Ground floor party walls have been completed.
Please see below the photos taken from the site: