Plastering and cladding completed. Tiling of wet areas near completion Stone benchtops are being installed. Joinery is being installed and near completion….
Mercer, January 2026
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Roof plumbing installation in progress
- Roof insulation near completion.
- Glass sliding doors in production.
- Insulation and plasterboards are being installed on ground floor. First and Second Floors completed.
- Lifts installation scheduled to start from the beginning of February.
- Render applied on First and Second Floors.
The estimated construction completion is Q2 2026.
We will continue to provide monthly updates as the project advances. Please see the latest site photos below.