Mercer, Feb 2025
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Entire ground floor concrete slab pour – Complete
- Ground floor wall framing for Units 6-8 – Complete
- Ground floor wall framing for remaining units – In progress