Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
Mercer, Dec 2024
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- The rear section of the ground floor slab has been successfully poured.
- Reinforcing steel and formwork are now in place for the remainder of the ground floor slab.
- Basement blockwork walls are nearing completion.
Please see below the photos taken from the site: