Units 6-10 ground floor framing complete Units 6-10 first floor framing and party walls in progress Basement hydraulic and mechanical services in…
Mercer, Apr 2025
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Basement hydraulic and mechanical services in progress
- Basement stud framing in place
- Ground floor framing complete
- Floor structure of first floor in progress for rear units
Please see below the photos taken from the site: