Lawson, August 2019
We are pleased to provide the progress achieved on site to date for Lawson.
– Framing has now been completed.
– Masonry block work has been completed.
– Scaffolding is up.
– Window is now installing.
We are still aiming for April 2020 construction completion timeframe at this stage.
We will keep you posted as we progress through the next phase.