– Townhouses 8 & 9 are up to the Second-floor frames– Townhouses 10-14 frames have all been completed– Windows have been installed…
Lawson, April 2019
We are pleased to provide the progress achieved on site to date for Lawson.
Shotcrete wall has been finished 100%. In-ground plumbing and civil works have been completed. Excavating the footings and preparation for the concrete to be poured after Easter
We will keep you posted as we progress through the next phase.