Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
Highmont, May 2022
We are pleased to share the construction progress for the Highmont project.
The following is the progress of the works to date:
- – Insulation for all units finished
- – Understairs doorway installed
- – Plaster wall and ceiling completed 80%
- – External cladding and render completed 80%
- – Internal waterproofing and tilling started
Please see below photos taken from the site.







