Basement hydraulic and mechanical services in progress Basement stud framing in place Ground floor framing complete Floor structure of first floor in…
Highmont, Mar 2022
We are pleased to provide the progress achieved on-site to date for Highmont, Bayswater.
The following is the progress of the works to date:
• Plywood installed to the steel frame for internal partition
• Rear cladding painted for the north side of the building
• Roof framing installed on the south side of the building
• Storm water pipe connected to an underground tank
Please see below photos taken from the site.




