Due to the shortage of raw materials across the industry, there have been some production and delivery delays of the LGS steel…
Highmont, Mar 2022
We are pleased to provide the progress achieved on-site to date for Highmont, Bayswater.
The following is the progress of the works to date:
• Plywood installed to the steel frame for internal partition
• Rear cladding painted for the north side of the building
• Roof framing installed on the south side of the building
• Storm water pipe connected to an underground tank
Please see below photos taken from the site.