Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
Highmont, April 2022
We are pleased to share the construction progress for the Highmont project.
The following is the progress of the works to date
- Skylight and glazed window installed
- External cladding and render completed 50%
- All internal stairs fixed, handrail to be installed
- Insulation for Unit 1-9 is finished.
- Plaster wall and ceiling completed 50%
Please see below photos taken from the site.






