Highmont, April 2022

  |  Construction Updates

We are pleased to share the construction progress for the Highmont project.


The following is the progress of the works to date

  • Skylight and glazed window installed
  • External cladding and render completed 50%
  • All internal stairs fixed, handrail to be installed
  • Insulation for Unit 1-9 is finished. 
  • Plaster wall and ceiling completed 50%

Please see below photos taken from the site.