Roof plumbing installation in progress Roof insulation near completion. Glass sliding doors in production. Insulation and plasterboards are being installed on ground…
GlenHolm, Sep 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Landscaping has commenced.
- Exterior bricklaying is currently in progress.
- Concreting is set to begin within the next week.
- Tiling is completed for TH01-TH07, with tiling in progress for TH08-TH12.
- The first layer of painting has been completed.
- Joinery installation has started across the site.
- Vanity installation is underway.
- Site measurements for stone benchtops and shower screens are complete, with production starting soon.
Please see below the photos taken from the site: