Wall framing complete Roof trusses in progress Plumbing stack work underway Please see below the photos taken from the site:
GlenHolm, Sep 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Landscaping has commenced.
- Exterior bricklaying is currently in progress.
- Concreting is set to begin within the next week.
- Tiling is completed for TH01-TH07, with tiling in progress for TH08-TH12.
- The first layer of painting has been completed.
- Joinery installation has started across the site.
- Vanity installation is underway.
- Site measurements for stone benchtops and shower screens are complete, with production starting soon.
Please see below the photos taken from the site: