Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
GlenHolm, Oct 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Concrete driveway has been completed, and landscaping is underway.
- Stone installations for the kitchen and vanity are complete, with plumbing fit-off in progress.
- All joinery work is complete, sliding doors are scheduled for installation later this week.
- Flooring installation has begun, and carpet is expected to be delivered later this week.
- A/C installation is planned for early November.
- Landscaping is expected to be finished by the end of November.
Please see below the photos taken from the site: