The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
GlenHolm, Nov 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Stone installations are now complete.
- All timber and carpet flooring has been installed, with the builder’s clean set to begin shortly.
- Air conditioning installation is finalised.
- Final touch-ups by the painter have commenced.
- Plants have been delivered to the site, and landscaping is expected to be completed within the next week.
Please see below the photos taken from the site: