GlenHolm, May 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Timber cladding panels have been installed, enhancing the exterior aesthetics.
- Hebel panels and fibre cement sheets are being installed, with rendering underway.
- Electrical and air-conditioning rough-ins are completed.
- Plumbing rough-in will be finished in the coming week.
- Bulkhead air-conditioning units have been installed.
- Wall insulation will be installed in the coming week.