With demolition complete and full excavation of the site finalised, the site cut is now nearing completion. Preparations are underway for pouring…
GlenHolm, Jun 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
-
Rough-in Completion: All rough-in work has been completed, ensuring essential infrastructure is in place.
-
Exterior Cladding: The installation of exterior cladding along the central driveway has been finished, enhancing both functionality and aesthetics.
-
Hebel Installation: The installation of Hebel panels throughout the project has been completed, contributing to improved insulation and energy efficiency.
-
Wall Insulation: Wall insulation has been installed, enhancing thermal performance and comfort within the building.
-
Balcony Waterproofing: Waterproofing for all balconies has been completed, ensuring durability and protection from the elements.
-
Upcoming: Wall Plastering: We are scheduled to commence wall plastering from next week, marking a big step towards the next stages of construction.