Roof plumbing installation in progress Roof insulation near completion. Glass sliding doors in production. Insulation and plasterboards are being installed on ground…
GlenHolm, Jul 2024
We are delighted to bring you the construction update for the GlenHolm development, showcasing the progress made on-site.
- Underground service installation in progress.
- Exterior rendering in progress, affected by heavy rainfall over the last few weeks.
- Staircase installation in progress.
- All plasterboards have been installed; wall plastering in progress.
- Bathroom waterproofing in progress.
- Façade waterproofing and tiling will commence next week.
- Joineries will be installed over the next month.
Please see below the photos taken from the site:





