Wall framing complete Roof trusses in progress Plumbing stack work underway Please see below the photos taken from the site:
Audrey, Nov 2024
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Bored piers are complete.
- Capping beams have been successfully installed.
- Retaining walls are now finished.
- Inground plumbing works are well underway.
- Bulk excavation for the basement is in progress.
Please see below the photos taken from the site:


