Audrey, Apr 2025
We are delighted to bring you the construction update for the Audrey Hawthorn development, showcasing the progress made on-site.
- Units 6-10 ground floor framing complete
- Units 6-10 first floor framing and party walls in progress
- Basement hydraulic and mechanical services in progress
- Basement ceiling insulation installed
Please see below the photos taken from the site: