The following is the progress of the works to date: External cladding – 95% completed Internal plasterboard installation 60% completed Internal staircase…
Ashton Park, Oct 2018
We are pleased to provide you with the progress achieved on site so far.
Building B, framing to level 1 is completed. The builder is starting to frame up level 2.
Building A, first-floor framing has started.