The rear section of the ground floor slab has been successfully poured. Reinforcing steel and formwork are now in place for the…
Ashton Park, June 2018
We are pleased to provide you with the progress achieved on site so far.
Block walls are getting build on building B.
Building A footing are getting excavated and poured.
Nbn conduits are laid and in-ground civil services are completed.